Bag-on-Valve (BOV) aerosol production requires a filling sequence that handles the product and propellant in separate compartments. The formulation is filled into a flexible bag, while the propellant occupies the space between the bag and the outer container. This arrangement requires coordinated assembly, sealing, pressurization, and product-filling operations.
The bag on valve filling process is not identical across all BOV products. The sequence depends on the propellant system, valve and bag design, formulation characteristics, and filling-line configuration. Compressed-gas systems commonly use under-the-cup pressurization, while liquefied-propellant systems may introduce propellant through the valve after crimping.
Understanding these differences helps product developers and brand owners evaluate manufacturing requirements before starting a BOV aerosol project.
What Is the Bag-on-Valve Filling Process?
The bag-on-valve filling process is the manufacturing sequence used to assemble and fill a BOV aerosol package. It places the product inside a flexible bag and introduces the propellant into the surrounding space inside the outer container.
The main parts have distinct functions:
- Flexible bag: Holds the product formulation and separates it from the propellant.
- Valve assembly: Connects the bag to the dispensing system and controls product discharge.
- Outer container: Houses the bag and propellant while containing the pressure required for dispensing.
- Propellant: Applies pressure to the outside of the bag, helping move the product toward the valve.
- Actuator: Opens the valve when operated and directs the discharged product.
When the actuator is pressed, pressure surrounding the bag compresses it. The formulation then travels from the bag through the valve and actuator. The product and propellant remain separated during normal storage and dispensing.
For a more detailed explanation of the structure and operating principle, see our guide to bag-on-valve technology.
BOV Filling Preparation: Components and Pre-Production Checks
Before production begins, the manufacturer needs to confirm that the selected packaging components and formulation are suitable for the intended BOV system. Problems with compatibility or component assembly can affect sealing, filling consistency, and dispensing performance.
Outer Container Inspection
The outer container must be suitable for the selected BOV assembly and intended operating conditions. Manufacturers may review its material, dimensions, opening configuration, surface condition, and compatibility with the valve mounting cup.
The container provides the external pressure boundary. Its design and structural suitability therefore need to be considered alongside the bag and valve assembly.
For more information about container construction, see aerosol can components.
Bag and Valve Assembly Preparation
The flexible bag is normally attached to the BOV valve as part of the packaging assembly. Depending on the system, the bag may be supplied already connected to the valve or handled as part of a dedicated assembly operation.
Before insertion, the assembly may be checked for visible damage, correct positioning, and suitability for the selected container. The valve configuration must also match the intended filling and dispensing arrangement.
The valve is not simply an interchangeable fitting. Its internal structure, sealing elements, and outlet configuration influence how the product moves through the package. See our guide to aerosol valve components for more information.
Formulation Preparation
The product formulation must be suitable for storage and dispensing inside the selected bag system. Relevant considerations include:
- Viscosity and flow behavior.
- Compatibility with bag materials and seals.
- Stability during storage.
- Potential interaction with valve materials.
- Dispensing requirements, such as spray, foam, or stream output.
A formulation that flows easily in a conventional aerosol package may behave differently when filled through a BOV valve into a flexible bag. Product development should therefore consider the complete packaging system rather than the formulation alone.
Learn more about aerosol formulation and the factors that affect product and package compatibility.
Equipment and Process Setup
The production line must be configured for the selected BOV assembly and propellant system. Preparation may involve checking component feeding, insertion, crimping, pressurization, product filling, and inspection arrangements.
Pre-production samples can help evaluate whether the selected formulation and packaging combination performs as intended before a larger production run.
Main Steps in the Bag-on-Valve Filling Process
The exact manufacturing sequence varies by BOV design and filling system. However, most production arrangements involve component insertion, valve attachment, propellant charging, product filling, and final inspection.
1. BOV Assembly Preparation and Insertion
The BOV bag and valve assembly is prepared for installation into the outer container.
Depending on the package design, the flexible bag may be folded, rolled, or otherwise arranged to fit through the container opening. Automated or semi-automated equipment can position and insert the assembly while helping maintain consistent handling.
Correct positioning matters because the bag must remain properly located inside the container. Poor insertion or damage to the assembly can affect later filling operations and the finished package.
The insertion method is not universal. It depends on the dimensions and construction of the BOV assembly, the container opening, and the equipment used.
2. Valve Crimping and Sealing
The valve assembly is secured to the outer container through its mounting cup. Crimping forms a mechanical connection between the mounting cup and the container opening.
The operation must establish a consistent attachment and support the sealing integrity of the package. Relevant process considerations include:
- Correct alignment of the valve and container opening.
- Compatibility between the mounting cup and container finish.
- Consistency of the crimping operation.
- Condition of the sealing components.
- Inspection of the finished connection.
The crimp is an important part of the package’s pressure boundary. A connection that is poorly formed or incompatible with the selected components may contribute to leakage or other quality problems.
For a closer look at this operation, see our guide to aerosol valve crimping.
The position of crimping within the filling sequence depends on the propellant system. In some compressed-gas arrangements, pressurization takes place before or during valve attachment. In common liquefied-propellant arrangements, the valve is crimped before propellant charging through the valve.
3. Propellant Charging and Pressurization
Propellant charging is one of the main differences between BOV production routes. The propellant must enter the space outside the flexible bag without being filled into the product compartment.
Two broad arrangements are used: compressed-gas systems and liquefied-propellant systems.
Route A: Compressed-Gas BOV Systems
Compressed-gas BOV systems commonly use air or nitrogen as the pressurizing medium, depending on the product and package requirements.
A common under-the-cup arrangement follows this general sequence:
- The BOV assembly is inserted into the outer container.
- Compressed gas is introduced into the space between the bag and container through an under-the-cup pressurization arrangement.
- The valve is crimped to the container as part of the configured filling sequence.
- The pressurized package undergoes an appropriate pressure check.
- The product is filled into the bag through the valve.
In this arrangement, the compressed gas is introduced around the bag rather than into the product itself. The pressure surrounding the bag provides the force needed to dispense the formulation.
Under-the-cup pressurization is a common approach, but it is not the only possible equipment configuration. The exact order of pressurization and crimping depends on the BOV system and production-line design.
A pressure check may be included after gas charging to verify that the package meets the process requirements. The method and acceptance criteria depend on the specific package and manufacturing procedure.
For more background on gas charging in aerosol production, see aerosol gas filling.
Route B: Liquefied-Propellant BOV Systems
Some BOV configurations use liquefied propellants instead of compressed gas. These systems require a different charging arrangement and suitable components and equipment.
A common process sequence may involve:
- Inserting the BOV assembly into the outer container.
- Crimping the valve assembly to the container.
- Introducing the liquefied propellant through the valve into the space outside the bag.
- Carrying out applicable purging, residue-removal, or valve-cleaning operations.
- Filling the product through the valve into the flexible bag.
The exact process depends on the valve design and filling equipment. Some systems incorporate vacuum purging or removal of residual propellant from the valve stem before product filling. These operations are configuration-dependent and should not be treated as mandatory steps for every BOV package.
Liquefied-propellant BOV systems demonstrate why manufacturers must confirm the intended filling route early in product development. A line configured for one propellant arrangement cannot automatically be assumed to support another.
For a broader overview of propellant choices, see aerosol propellant types.
4. Product Filling Through the Valve
Once the propellant system has been prepared, the product formulation is introduced through the valve into the flexible bag.
The filling equipment connects to the valve and delivers the formulation through the valve stem and into the bag. The product remains inside the bag, while the propellant stays in the surrounding space.
Several factors influence this operation:
Formulation viscosity: More viscous products may require different filling arrangements from low-viscosity liquids. The valve passage, filling equipment, and formulation flow behavior must work together.
Component compatibility: The formulation must be compatible with the bag material, seals, and relevant valve components. Compatibility should be evaluated for the complete package rather than one component in isolation.
Filling consistency: The product quantity needs to remain within the defined production requirements. Weight or fill-quantity checks may be incorporated into the filling process.
System configuration: The filling conditions depend on the BOV design and selected propellant route. There is no single filling pressure, speed, or operating condition suitable for every BOV product.
The product-filling stage is therefore closely connected to formulation development, valve selection, and package design.
5. Post-Filling Inspection and Packaging
After product filling, the package moves through the remaining production and inspection stages. The exact checks depend on the product, package configuration, and applicable manufacturing requirements.
Potential quality-control activities include:
- Visual inspection of the container, valve, and actuator.
- Checking the valve attachment and crimping condition.
- Verifying product fill quantity or package weight.
- Pressure-related checks where applicable.
- Leakage or sealing checks using suitable procedures.
- Dispensing evaluation when required by the product specification.
- Inspection of the actuator, cap, label, and final packaging.
These are general manufacturing considerations, not a universal test sequence. The appropriate inspection plan should be established for the specific BOV product and production process.
Once the required checks are completed, the packages can proceed to final assembly and packing. This may include actuator and overcap installation, labeling, carton packing, and preparation for shipment.
Compressed Gas vs. Liquefied Propellant: How the Filling Process Differs
Both systems keep the product inside the bag and the propellant outside it. Their main difference lies in how the propellant is introduced and how the filling sequence is organized.
| Process consideration | Compressed-gas BOV | Liquefied-propellant BOV |
|---|---|---|
| Propellant type | Compressed gas, commonly air or nitrogen | A suitable liquefied propellant |
| Common pressurization arrangement | Under-the-cup pressurization | Through-the-valve propellant charging |
| Valve attachment | May follow or be integrated with under-the-cup pressurization | Commonly completed before propellant charging |
| Product filling | Through the valve into the bag | Through the valve into the bag |
| Additional process considerations | Pressure verification and gas-charging consistency | Propellant residue removal or purging where required |
| Main selection factors | Product requirements, package design, and gas-system compatibility | Product requirements, package design, and liquefied-propellant compatibility |
These routes are not interchangeable without the appropriate BOV components, filling equipment, and process configuration. The selection should be made according to the formulation, intended dispensing performance, packaging design, and manufacturing requirements.
Equipment Used in BOV Aerosol Filling
A BOV production line combines several equipment categories to handle assembly, pressurization, filling, and final packaging. The exact configuration varies with the package design and propellant system.
Common equipment categories include:
- BOV insertion equipment: Handles and positions the bag and valve assembly inside the outer container.
- Valve crimping equipment: Secures the valve mounting cup to the container opening.
- Propellant charging equipment: Introduces compressed gas or liquefied propellant according to the selected system.
- Product filling equipment: Delivers the formulation through the valve and into the flexible bag.
- Inspection equipment: Supports applicable checks of fill quantity, pressure, package condition, or dispensing performance.
- Final assembly and packaging equipment: Handles actuator and cap placement, labeling, and packing.
Coster’s BOV filling machine brochure provides examples of equipment configurations for both compressed-gas and liquefied-propellant BOV systems. Its illustrated arrangements are manufacturer-specific examples rather than universal production-line requirements.
The filling equipment must be selected and configured around the BOV package and production process. A machine designed for one type of BOV system may not be suitable for another without the required configuration and component compatibility.
Common Process Considerations in BOV Manufacturing
A consistent BOV manufacturing process depends on more than the filling equipment. The bag, valve, container, propellant, and formulation must function as one packaging system.
Bag and Valve Compatibility
The bag material must be suitable for the formulation and intended storage conditions. The valve assembly must also support the required filling and dispensing behavior.
Compatibility should be evaluated across the complete package, including seals and other contact materials.
Component Positioning and Crimping
The bag and valve assembly must be inserted and positioned correctly. The valve must then be attached in a way that supports the package’s mechanical and sealing requirements.
Inconsistent positioning or crimping can affect later production stages and package integrity.
Propellant Selection
Compressed gases and liquefied propellants have different physical properties and filling requirements. The selected propellant influences the charging method, process sequence, and compatibility requirements.
Brands should define the intended propellant system before finalizing the filling process.
Formulation Viscosity and Filling Behavior
The formulation must flow through the selected filling system and valve into the bag. Viscosity, formulation stability, and material compatibility can all influence the process.
Products with different physical characteristics may require different filling arrangements.
Process Control and Inspection
Production checks help identify issues related to component assembly, fill quantity, pressure, sealing, and finished-package appearance.
The inspection plan should reflect the actual product requirements and the capabilities of the manufacturing line. General production checks should not be confused with specialized laboratory testing or certification.
Choosing a BOV Aerosol Filling Company
Selecting a BOV filling partner involves more than confirming that a manufacturer has a BOV production line. Brands should evaluate whether the manufacturer can coordinate the formulation, packaging components, filling requirements, and quality checks for the intended product.
Consider the following points when assessing potential partners:
- BOV production experience: Confirm that the manufacturer has experience handling BOV packaging and understands the differences between propellant systems.
- Formulation support: Ask whether the manufacturer can develop or adjust formulations and assess their suitability for the selected package.
- Packaging coordination: Discuss the availability and compatibility of the bag, valve, container, actuator, and other packaging components.
- Production capabilities: Confirm which BOV production arrangements the manufacturer can support. Do not assume that every BOV filling company handles every propellant system.
- Quality-control procedures: Understand how incoming materials, production operations, and finished products are checked.
- Pre-production samples: Where applicable, evaluate samples before committing to mass production.
- Project communication: Confirm how technical requirements, packaging decisions, sample feedback, and production arrangements will be coordinated.
BOV Aerosol Manufacturing Support from TENTOP CHEM
Established in 2007, Zhongshan Tentop Fine Chemical Co., Ltd. (TENTOP CHEM) provides aerosol OEM/ODM and private-label manufacturing services in Zhongshan, Guangdong, China.
The company operates four high-speed aerosol filling lines, three BOV aerosol production lines, and two liquid filling lines. Its services include formulation development and adjustment, BOV aerosol production, packaging coordination, and production quality checks.
For brands developing a new BOV product, the project can involve reviewing the formulation, discussing suitable packaging components, coordinating pre-production samples, and confirming production requirements before mass manufacturing.
You can learn more about TENTOP CHEM’s aerosol contract manufacturing and private-label services. Specific BOV filling arrangements should be discussed and confirmed according to the product and packaging requirements.
Conclusion
The bag on valve filling process involves several coordinated stages, from preparing and inserting the bag-valve assembly to crimping, propellant charging, product filling, and final inspection.
The most important process distinction is the propellant system. Compressed-gas BOV products commonly use under-the-cup pressurization, while liquefied-propellant configurations may use through-the-valve charging. The exact sequence depends on the package design and filling-line configuration.
For brands planning a BOV aerosol project, formulation compatibility, component selection, production capabilities, and quality-control arrangements should be considered together. Contact TENTOP CHEM to discuss your product requirements, packaging options, and potential BOV aerosol manufacturing project.